Project Summaries December 3, 2007
Streets & Drainage Projects
- Phase II Stormwater Compliance - Mandates from Federal EPA and Tennessee Department of Environment & Conservation (TDEC)
- Illicit Discharge Detection and Elimination - Revising City ordinance to comply with last TDEC audit.
- Construction Site Storm Water Runoff Control - Revising City ordinance to comply with last TDEC audit.
- Post-Construction Storm Water Management
- Buffer Ordinance - Draft ordinance for streamside buffers is being reviewed internally by City staff. Goal is to present the ordinance to the Board of Commissioners (BOC) at their January 2008 and February 2008 meetings.
- Post-Construction Ordinance & Manual - Preparing Alcoa ordinance and manual utilizing info from Metro Nashville & Knox County manuals. Goals: BOC review in Jan & Feb 2008.
- Pollution Prevention / Good Housekeeping for Municipal Operations - Developing manual for regularly scheduled training of City employees.
- Stormwater Utility - Options for funding of stormwater compliance are either tax rate or a separate utility. Utility option is being pursued.
- TMDL Development (Total Max. Daily Loads of stream pollutants) - Monitoring plan approved by TDEC.
- Pellissippi Pkwy Extension - OK Hwy to US 321 - Per July 2007 Transportation Planning Organization (TPO) meeting, right-of-way acquisition in 2010.
- Alcoa Hwy Improvements - Pellissippi Pkwy to County Line - Per July 2007 TPO meeting, right-of-way acquisition in 2010.
- Alcoa Parkway - Per July 2007 TPO meeting, right-of-way acquisition in 2010.
- Sam Houston School Rd Intersection Improvements - Initial Consultant: Kimley Horn.
- Geometric Improvements - Complete.
- Signal Improvements - Holley Electric. Work underway.
- Alcoa Hwy / Wright Rd Intersection Improvements - Learned from TDOT off additional requirements w.r.t. right-of-way certification, utilities, etc.
- Alcoa/Maryville Traffic Signal Coordination & Communication Improvements - Advanced Traffic Management System (ATMS) Master Plan - Consultant: Kimley-Horn Associates. CMAQ funding application made to TPO; $126k included in TPO's FY 2008 work plan.
- Topside Rd Corridor Traffic Study
- Phase 2 - Widening of Topside Rd - Contractor: Harrison Construction. Widening to begin 1/15/08. Water line relocation by City to be completed 12/07.
- Middlesettlements Rd Improvements - Complete right-of-way acquisitions Fall 2008. Bid Fall/Winter 2008; start const early 2009; complete const late 2010 / early 2011.
- Old Knoxville Hwy / Pellissippi Pkwy Traffic Signal Improvements - Warrants approved by TDOT. Gresham Smith & Partners involved as TDOT liaison. TDOT has committed to proceed with design & installation.
- Hall Rd / CSX Crossing Repairs - Started Spring 2007 by CSX; left unfinished. Street Supervisor to make weekly calls to CSX until finished.
Water & Wastewater Projects
- WTP Membrane Filters, Lab Bldg, & Appurtenances - Complete. Minor punch list items remain.
- WTP Demolition - Contractor: Southern Constructors / Total Demolition Services. Underway.
- WTP Lagoon No. 2 - Low Bidder: WBS, Inc.Fencing Contract - Include as separate contract in Service Center fencing bid.
- WTP Auxiliary Raw Water Intake - Cooperative project with City of Maryville.
- Phase 1 - Temporary Installation - Morgan Contracting. Temporary pumps & line installed and operating. Acquiring easements for permanent installation of line.
- Phase 2 - Permanent Installation of Raw Water Line - Specifics being prepared. Target installation to begin 3/01/08 with Martin Mill Pk closure week of 3/17.
- Alcoa / Maryville Water Systems Development, Expansion & Interoperation - RFQ issued. Pre-submittal conference 12/20/07. Statements of Qualification due 1/08/08.
- Wildwood / Rockford Area, Phase 2B: Little River to Stock Ck. - Consultant: Vision Engineering. Contractor: Mike Smith Pump. Complete. 1st as-builts received. Contractor replacing curbing at Littlebrook S/D.
- Springfield Br Sanitary Sewer Improvements - Consultant: Sterling. Contractor: Garney Construction. Complete except for paving, minor punch list items, and stabilization.
- Regional Wastewater Treatment Plant (RWWTP) Expansion - RWWTP jointly owned by Alcoa and Maryville; operated and managed by Maryville. Consultant: JR Wauford & Co.
- Expansion plans 95% complete.
- RWWTP Utility Relocations - 12" W.L.; Island Home Force Main Relocation of Alcoa lines to accommodate expansion of RWWTP.
- Middlesettlements Rd - 1200 Block San Sewer Ext - Complete. Need as-builts.
- Nean Lane Tank Site Abandonment - Initial title research completed by City Attorney. Survey complete by Sterling. Will likely maintain ownership but short-term lease to adjoining property owners. Iron pins to be concreted by Engineering staff.
- W. Bell St San Sewer Rehab / Ext. - Low pressure sewer line installed.
- US 129 / Louisville Rd 12-in WL Ext. - Extension to improve Hamilton Crossing fire flow. Underway.
- Goddard St San Sewer Rehab Carroll & Ross - Leadworker: Ogle. On hold for gas line relocation.
- Air Base Rd / Air Base Entrance WL Relocation - TANG-funded project. C2RL, Inc. design meetings complete.
- Middlesettlements Rd WL Relocation - Hunters Crossing to Mt Tabor - Consultant: Barge Wagonner Sumner & Cannon.
- Airport Operations - Sanitary Sewer Rehab - Replace exist sanitary sewer along SW corner of MKAA property. Underway.
- Topside Rd / Marriott Dr Water Line Relocation - Relocate & upgrade water line on Topside Rd between Marriott Dr and Lark Cir. Materials delivered. To be completed prior to Christmas.
- McGhee Tyson Airport San Sewer Rehab - Study of rehab needs by MKAA of airport's sanitary sewer system. Engineering assistance provided by C2RL.
Greenways/Sidewalks/Parks Projects
- Pistol Ck Greenway Phase III – Springbrook Rd to Meadowwood Apts. - On hold until approval received for Culton Ck Greenway.
- Culton Ck Greenway, Phase I – SCC to St Ives, Phase II - SCC to Greenmeadow, Phase III - Greanmeadow to Andover. - Louisville Rd sidewalk approved. Proceeding with design, environmental reviews, etc.
- Environmental Reviews / Permits
- ARAP Permit - Permit received.
- TDEC General Permit - Permit received.
- Corps of Engineers Permit - Permit received.
- CSX Permit - CSX comments received. Completing detailed design.
- Native American Review - Final review before CE.
- TDOT Categorical Exclusion - Awaiting issuance - no work may progress without CEEasement Acquisition - Stake & review with owners. Title info forwarded to City Attorney. Per TDOT property acquisition procedures, cannot make contact without CE.
- Design & Construction - Will begin construction after (1) categorical exclusion received from State and (2) completion of easement acquisitions.
- Greenway, Pistol Ck Phase IV - Meadowood to Alcoa Trail - Grant approved by TDOT. Met w/ Alcoa, Inc. and TDEC staff regarding routing to avoid / minimize environmental concerns.
- Greenway Bridge - US 129 Bypass - A&E: Wilbur Smith Associates & Ross/Fowler Architects. 95% plans review complete.
- Environmental Reviews / Permits
- Historical Review - Information submitted.
- Endangered Species Review - Approved.
- TDEC General Permit
- Corps of Engineering Permit
- Native American Review
- TDOT Categorical Exclusion
- Springbrook Park - Sign for upper fields @ Hunt Rd - Design underway.
Landfill
- Landfill - Expansion of Permit Areas - Holloway, Wiggins. Consultant: Lukens Engineering. Part I application approved by BOC and delivered to TDEC at 8/02/06 meeting with TDEC. Strata hydrogeologic report received 8/02/07.
- Slope Repairs - Class III/IV South Slope - Holloway. Consultant: Lukens Engineering. Plans received by LF staff. Evaluating bid or in-house construction.
- Alcoa, Inc. Methane Recovery Project. - Initial data collection by Alcoa, Inc.
- Denso / Hodge Engineering Methane Recovery Project - Summary meeting held with Denso and Hodge staff.
Miscellaneous
- Service Center - C2RL Engineers / Architects International
- General Contract - Contractor: Blaine. Office / Warehouse: Steel erection complete; interior framing, electrical, plumbing, HVAC underway. Vehicle Storage: Steel erection complete; roofing underway.
- Demolition Contract - Complete.
- COA - Sanitary Sewer - Complete.
- COA – Water - Complete.
- COA - Storm Sewer - Complete.
- COA – Electric - Complete
- Fencing Contract - Specifics being prepared.
- Landscaping Contract - Met with Linginfelter Contracting, re: modifications to planting plans.
- Recycling Drop-Off - Relocation of drop-off site.
- Completed Components
- PreDryer Bldg - Completed. Temporarily occupied by Walker Supply
- Bulk Storage Bldg - Complete. COA crews removing roof insulation; repair areas identified in roof.
- Pole & Pipe Yard - Complete except for salt bin and lighting.
- Service Center - Acquisition of Alcoa, Inc. Property for BCHD - Purchase offer made & tentatively accepted. Survey complete. Plat approved by ARPC; forwarded to Alcoa, Inc. for signature.
- GIS / GPS
- Develop common symbology - Complete.
- Aerial Photography - State contract. Re-flown Winter 07. Mapping being developed.
- Mapping – Storm System - Complete
- Mapping – Sewer System - Substantially complete.
- Mapping – Water System - Substantially complete.
- Inventory – Water Lines
- Website Development - Test site launched.
- Bassel Bell Tower Monument - Monument of installation and preservation of bell tower from Bassel School. Bell tower painted to hinder further deterioration.
- Right-of-Way Permit Program - On hold.
Development Projects
- Hamilton Crossing Bldg D - Underway
- Airport West Development Area - Preconstruction held for grading. Contractor needs to schedule preconstruction for water and sewer.
- Grading & Drainage - Phillips & Jordan - Hauling from Partnership North resumed.
- Water & Wastewater - P&J / Blount Excavation - Sewer complete; water +/- complete.
- Tyson Centre – Underway.
- Base Pointe - Underway.
- Access Rd West Extension - Water, sewer, streets, drainage complete. Site stabilized but "dormant."
- Office/Warehouse Buildings (2)
- St Ives, Phase IV - Water, Sewer, Streets, Drainage - Complete except for asphalt surface, seeding, etc.
- Marriott Headquarters Expansion - Complete except for detail work.
- St. Thomas Subdivision (Northwood) - Development of property at dead-end of Tsuga in Northwood. Streets & Drainage - Complete except for asphalt surface, seeding, etc.
- Top Gun Customs - Regal Dr - Underway.
- Lynn's Landing Condos - Red Hill Dr / Hillside Dr - Water & sewer complete.
- Topside Wine & Spirits - Underway.
- Andover Phase 5 - Sharp Contracting. Water & sewer +/- complete. Base stone placed.
- Blount County Highway Department Maintenance & Engineering / BC Schools Maintenance - Design underway by Hodge Engineering.
- Middlesettlements Rd / Walker Supply - Water & sewer complete. Base stone placed.
- Airport - ARFF Water & San Sewer Extensions - New Air Rescue & Firefighting Facility. W&S extensions and looping of water system. Underway.
- Jones Bend - The Reserve on the Tennessee River - Road graded. Water line complete except for testing.
- Green Meadow Wine & Spirits - Grading underway.
- TN Urology Associates - King's Court - Grading underway.
- Middlesettlements Rd - Legends @ Hamilton Park - Plans submitted & reviewed.
- Cusick Rd - Candlewood Suites - Plans submitted & reviewed.
- Lincoln Rd - CVS Pharmacy - Preconstruction conference held.
|